Project Name |
Lighting Improvements at Steep Bank Creek Pump Station |
Short Project Description |
Add lighting structures at the pump station to improve visibility for emergency operations. |
Additional Technical Information |
District engineer designed these upgrades into the expansion project and was constructed under the Pump Station contract as an add-in project. |
Estimated Total Project Cost (including engineering and contingency) |
Included in the project ‘Steep Bank Creek Pump Station Expansion’. |
Estimated LID 19 Cost and Sharing Basis |
The project was shared between the District and Fort Bend County LID 15. |
Project Status |
Completed in 2023 |
Financing Source |
Financing was done by both LID 15 and 19 in the Pump Station expansion contract. |