Status Report on Post-Harvey Action

LID 19’s Board has been notified that the Phase 1 of the third party engineering report will be delivered by the end of this month.  The results of the report will be posted here.  In addition, several improvement projects are underway.

  • Capital Projects:
    • Temporary supplemental pumps (purchased together with LID 15 to provide a total of 80,000 additional gpm) – ordered, June 2018 anticipated delivery.
    • Pump Station at Snake Slough – currently under design.
    • Interconnect for Snake Slough/Steep Bank Creek – currently under design.
    • Interconnect for Alcorn Bayou/Steep Bank Creek – currently under design.
    • Pump Station at Lost Creek – in discussion with other districts within Steep Bank Creek watershed for regional participation.
  • Operations
    • Staff gauges at Steep Bank Creek pump station – ordered
    • Digital emergency bulletin boards – in review
    • Expansion of emergency alert system (text messages, emails, and voicemail) – underway
    • Development of improved communications protocol and website modifications – underway

Additional projects are being considered by the District.  A comprehensive update will be posted here in June 2018.  The LID Board is also working to schedule a community open house meeting in May 2018.